The Formula, Step by Step
There is only one concrete calculator formula behind every tool on this site, and it runs in four steps.
Step 1: Get every dimension into feet. Divide thickness in inches by 12, so 4 in equals 0.333 ft and 6 in equals 0.5 ft. Most hand estimates fail here: a 10×10 slab at 10 × 10 × 4 gives 400, not the real 33.33 ft³.
Step 2: Multiply for cubic feet. For a slab, multiply length by width by thickness, and for a round pour, multiply π by radius² by thickness (radius equals half the diameter). For a footing, multiply length by width by depth, and for post holes, multiply π by radius² by depth by the hole count.
Step 3: Divide by 27 for cubic yards. Ready-mix plants sell concrete by the cubic yard (27 ft³). The yards calculator shows ft³, yd³, and m³ side by side and accepts metric input on every field.
Step 4: Add waste and round up. Add 5 to 10 percent (more for rough work), then round to the plant batching increment, typically a quarter yard. A second delivery for a shortfall costs several times the price of the extra quarter yard.
Common Pours at a Glance
| Project | Exact volume | Order this | 80 lb bags instead |
|---|---|---|---|
| Patio slab 10×10 ft, 4 in | 1.23 yd³ | 1.5 yd³ | 56 bags |
| Shed pad 12×12 ft, 4 in | 1.78 yd³ | 2 yd³ | 80 bags |
| Garage slab 20×20 ft, 4 in | 4.94 yd³ | 5.5 yd³ | 223 bags |
| Driveway 16×40 ft, 5 in | 9.88 yd³ | 10.5 yd³ | 445 bags |
| Footing 40 ft, 16×8 in | 1.32 yd³ | 1.5 yd³ | 60 bags |
| Deck pier, 12 in sonotube, 4 ft (each) | 0.12 yd³ | Use bags | 6 bags |
| Post hole 12 in dia, 3 ft (each) | 0.09 yd³ | Use bags | 4 bags |
The driveway row deserves a second look: 16 × 40 ft at 5 in equals 266.67 ft³, or 9.88 yd³, close to a full truck. Thickness is the lever: the same driveway at 4 in would be 7.90 yd³, and at 6 in, 11.85 yd³. Choose thickness by load (4 in for foot traffic and patios, 5 to 6 in for vehicles), not by rounding instinct.
Bags or a Ready-Mix Truck?
The crossover sits at about one cubic yard. One yard in bags means 45 × 80 lb sacks, roughly 3,600 lb of dry mix to transport, open, mix, and place. Bags win for post holes, repairs, and pours under a yard, where truck minimums and short-load fees punish small orders.
Above a yard, the math flips: mixing time stretches past the concrete working window. Early batches start setting before you place late ones, creating cold joints, and bags cost more per yard than delivered ready-mix. Use the bag calculator for your count, then price it against a truck in the cost calculator before deciding.
Five Ways Estimates Go Wrong
- Convert thickness first. Treating inches as feet creates a 12× error.
- Add waste. Exact geometry assumes perfect forms on perfect grade, and neither exists on a real site.
- Count the base separately. A 4 in gravel base under a slab needs its own quantity, so run the gravel calculator for it.
- Halve the diameter. Round pours need radius, which equals diameter divided by 2, before you square it, and using diameter quadruples the estimate.
- Check minimums and fees. A 1.25 yd³ order can cost like 2 yd³ once short-load fees land, so ask the plant before you finalize.
Strength, Mix and the Rest of the Order
Volume is only the quantity question. Tell the plant the strength you need: 3,500 to 4,000 PSI covers most residential flatwork, and footings and structural elements follow your local code.
If you are batching by hand, the mix calculator turns yards into cement bags, sand and aggregate by ratio (the classic general-purpose ratio is 1:2:3). Remember the steel: mesh or a rebar grid reinforces vehicle slabs, and that steel adds a separate quantity without changing concrete volume.