Concrete Bag Calculator

Enter the size of your pour and this bag concrete calculator tells you how many pre-mix bags to buy. It reports all four standard sizes: 40, 50, 60, and 80 lb. You can compare what sits on the store shelf instead of guessing in the aisle.

Free · Instant results as you type · No sign-up

1Dimensions

4 in for patios and walkways, 5 to 6 in for driveways.

2Waste allowance

%

Pros order 5 to 10% extra for spills, over-excavation and uneven subgrade.

3Material and cost

Delivered ready-mix commonly runs $150 to $200 per yard before fees. Leave at 0 to skip cost.

Live preview

10 ft10 ft4 in

Your estimate

Updates as you type
Pre-mix bags, 80 lb59 bags
Order this (rounded up)1.50 yd³Plants sell concrete in quarter-yard steps, so this rounds your figure up.
Volume (cubic feet)35.00 ft³
Volume (cubic meters)0.99 m³
Footprint area100.0 ft²
Waste amount0.06 yd³
60 lb78 bags
50 lb94 bags
40 lb117 bags
Weight (at 150 lb/ft³)5,250 lb

Includes a 5% waste allowance on top of the exact geometric volume (1.23 yd³). Bag counts are rounded up, because you cannot buy part of a bag.

The tool suits the jobs bags actually handle: post holes, small pads, walkways, patches, and footings under a cubic yard. As a bagged concrete calculator, it assumes pre-mix sacks throughout, not site-mixed concrete.

Stores sell bags by weight, but crews place concrete by volume, and each bag's yield fixes the conversion. An 80 lb bag of Quikrete or Sakrete pre-mix makes 0.60 cubic feet of wet concrete. A 60 lb bag makes 0.45 ft³, a 50 lb bag 0.375 ft³, and a 40 lb bag 0.30 ft³.

Every count here divides your pour's volume by that yield and rounds up, because no one can split a bag across trips to the store. That single yield answers the most common bag question, how many 80 pound bags of concrete in a yard: 27 ÷ 0.60 = 45.

How This Calculator Works

A bags of concrete calculator first works out your pour's volume in cubic feet. It multiplies length × width × thickness, converts inches to feet, and adds your waste allowance. Then it divides by the yield of each bag size and rounds counts up to whole bags.

Regional names change nothing. Whether you think of it as a sack concrete calculator or a bag calculator, the yields below are the whole method.

The practical limit for bags is about one cubic yard. One yard is 45 × 80 lb bags. A small crew with a rented mixer can handle that load in a heavy Saturday.

Two yards is 90 bags and roughly 7,200 lb of dry mix. Someone must lift, open, mix, and place all of it before the first batches start to set. Past one yard, a ready-mix truck is almost always cheaper per cubic foot and produces more consistent concrete.

For pallet orders, standard counts are 42 bags for 80 lb and 56 for 60 lb. Counts run 64 for 50 lb and 80 for 40 lb. A pallet of 80 lb bags weighs about 3,360 lb plus the pallet, so plan the vehicle or delivery accordingly.

Formula: Bags needed = (Length × Width × Thickness in ft³) × (1 + waste %) ÷ yield per bag (80 lb: 0.60 ft³, 60 lb: 0.45 ft³, 50 lb: 0.375 ft³, 40 lb: 0.30 ft³)

Worked Example: Bags for a 10 × 10 ft slab, 4 in thick

Bar chart of yield per bag: 40 lb makes 0.30, 50 lb 0.375, 60 lb 0.45 and 80 lb 0.60 cubic feet
Divide your volume in cubic feet by the yield, then round up.
  1. Volume: 10 × 10 × (4 ÷ 12) = 33.33 ft³, or 1.23 yd³.
  2. 80 lb bags: 33.33 ÷ 0.60 = 55.6, rounded up to 56 bags.
  3. 60 lb bags: 33.33 ÷ 0.45 = 74.1, rounded up to 75 bags.
  4. 50 lb bags: 33.33 ÷ 0.375 = 88.9, rounded up to 89 bags.
  5. 40 lb bags: 33.33 ÷ 0.30 = 111.1, rounded up to 112 bags.

Result: 56 × 80 lb bags give the fewest trips and usually the lowest cost per cubic foot. The smaller sizes take 75, 89, or 112 bags.

Bags of Concrete per Cubic Yard, and Coverage per Bag

Bag sizeYield per bagBags per cubic yardCoverage at 4 in thickBags per pallet
40 lb0.30 ft³90 bags0.90 ft²80 bags
50 lb0.375 ft³72 bags1.13 ft²64 bags
60 lb0.45 ft³60 bags1.35 ft²56 bags
80 lb0.60 ft³45 bags1.80 ft²42 bags

Frequently Asked Questions

How many 80 lb bags of concrete are in a cubic yard?

Forty-five: one cubic yard is 27 ft³, and an 80 lb bag yields 0.60 ft³, so 27 ÷ 0.60 = 45. The same yard takes 60 × 60 lb bags, 72 × 50 lb bags, or 90 × 40 lb bags. To answer how many 80 lb bags of concrete in a yard of any shape, divide the pour's cubic feet by 0.60.

How many bags of concrete are on a pallet?

An 80 lb pallet holds 42 bags, a 60 lb pallet 56, a 50 lb pallet 64, and a 40 lb pallet 80. If you count how many 80 lb bags of concrete on a pallet for a delivery or truck bed, the answer is 42. That pallet holds roughly 3,360 lb of mix, plus the pallet itself.

How much does a bag of concrete cost?

A standard 80 lb bag of pre-mix typically runs about $4 to $7 at US home centers. Bags of 60 lb run about $4 to $6, 40 lb bags about $3.50 to $5, and fast-setting or high-strength mixes cost more. The 80 lb bag of concrete price per cubic foot is the lowest, but bag of concrete cost is only half the comparison.

How many bags of concrete do I need for a 10×10 slab?

At 4 in thick (33.33 ft³), you need 56 × 80 lb bags or 75 × 60 lb bags before waste. The smaller sizes take 89 × 50 lb or 112 × 40 lb bags. That is over a yard of concrete, so compare the bag total against a ready-mix delivery before you commit.

How much water goes in each bag?

Roughly 3 quarts for an 80 lb bag, scaling down with bag size (about 2 quarts for 60 lb). Start below the bag's stated maximum and add small amounts. Soupy concrete loses strength fast, because excess water raises the water-cement ratio.

Are bag counts different for Quikrete and Sakrete?

No. Both brands rate standard pre-mix bags at the same yields: 0.60 ft³ (80 lb), 0.45 (60 lb), 0.375 (50 lb), and 0.30 (40 lb). High-strength and crack-resistant mixes use the same yields; fast-setting mixes are very close.

When should I stop using bags and order ready-mix?

Stop around one cubic yard: below that, bags win on convenience and minimum-order fees. Above it, labor, mixer rental, and the inconsistency of hand mixing cost more than a short-load delivery. A truck places the whole pour at once, which means no cold joints.