To calculate concrete for a slab, multiply length × width × thickness in feet and divide by 27. A 16 × 12 ft shed slab at 4 inches thick, for example, holds 64 ft³. That volume equals 2.37 cubic yards.
Add a waste allowance and round up, and you order 2.75 yards. That one formula covers every rectangular slab:
- Patios
- Shed bases
- Garage floors
- Walkways
- Driveways
If you would rather skip the arithmetic, the concrete slab calculator does it instantly, including waste. But understanding the steps protects you from the two mistakes that actually cause short pours: bad thickness conversion and a bad subgrade.
Step 1: Measure and check the site is square #
Measure the inside of your forms, not the outside, in feet. Measure both directions in two places; excavations and form boards are rarely as straight as they look.
Then check the site is square with the diagonal test: measure corner to corner in both directions. On a square or rectangular slab, the two diagonals are equal.
If one diagonal is longer than the other, your forms are racked into a parallelogram. The area and your concrete volume still equal length × width. But the slab will sit visibly out of square against a house, fence, or driveway edge.
Fix the forms before the pour, not after. Pull the diagonals equal and stake the corners again.
Round measurements up to the nearest inch, never down. An extra inch of length costs a trivial amount of concrete; an inch short is built into the slab forever.
Step 2: Convert thickness to feet #
This is where most home calculations go wrong. Thickness is measured in inches but the formula needs feet:
- 4 inches = 4 ÷ 12 = 0.333 ft
- 5 inches = 0.417 ft
- 6 inches = 0.5 ft
Four inches is the standard thickness for patios, walkways and shed slabs. Six inches is typical for driveways and garage floors that carry vehicles.
Never plug "4" into the formula as if it were feet. That error multiplies your order by twelve.
Step 3: The worked example: a 16 × 12 ft shed slab #
Here is the full calculation for a 16 × 12 ft shed slab, 4 inches thick, start to finish:
- Area: 16 ft × 12 ft = 192 ft²
- Volume in cubic feet: 192 × 0.333 = 64 ft³
- Convert to cubic yards: 64 ÷ 27 = 2.37 yd³
- Add 10% waste: 2.37 × 1.10 = 2.61 yd³
- Round to an orderable amount: ready-mix is typically ordered in quarter-yard steps, so order 2.75 yd³.
Doing the same slab in bags instead: 64 ft³ ÷ 0.60 ft³ per 80 lb bag = 107 bags before waste. With waste, you would actually buy roughly 118 bags. That is well past the point where a ready-mix truck makes more sense for most people, as the bags per yard chart makes clear.
Bags come on pallets of 42 in the 80 lb size. A bag pour this size means close to three pallets to move and store.
The formula in one line:
Cubic yards = (Length in ft × Width in ft × Thickness in ft) ÷ 27
Common slab sizes at 4 inches thick #
Use this table for a fast estimate, then add waste before ordering.
| Slab size | Volume | Cubic yards (exact) |
|---|---|---|
| 8 × 8 ft | 21.3 ft³ | 0.79 yd³ |
| 10 × 10 ft | 33.3 ft³ | 1.23 yd³ |
| 12 × 12 ft | 48 ft³ | 1.78 yd³ |
| 16 × 12 ft | 64 ft³ | 2.37 yd³ |
| 20 × 20 ft | 133.3 ft³ | 4.94 yd³ |
A useful coverage check: one cubic yard covers 81 ft² at 4 inches thick, or 54 ft² at 6 inches. If you know the area and thickness, dividing by 81 (or 54) is the fastest estimate you can do standing in the yard.
For 6-inch slabs, multiply the 4-inch yardage by 1.5. The 10 × 10 slab goes from 1.23 to 1.85 yd³; the 20 × 20 goes from 4.94 to 7.41 yd³. The concrete slab calculator handles any thickness, including the thickened edges some garage and shed slabs need.
Step 4: Add waste and know what it covers #
Add 10% for a typical slab on a well-prepared base. Treat 5% as the floor for a perfect site with experienced finishers. And 15% is not excessive for a first pour on rough ground.
Waste is not a fudge factor. It covers real, predictable losses:
- Concrete left in the truck chute, pump or wheelbarrow
- Spillage at the edges and overfilled low spots
- Forms that bow slightly outward under the weight of wet concrete
- The extra depth everywhere the base sits a fraction low
Order in the increments your supplier sells, usually quarter yards, and always round up. Running short mid-pour is the one unrecoverable error in a slab. The truck's second trip arrives against concrete that has already started to set.
That delay leaves a cold joint and a visible seam. An extra quarter yard left over is a small disposal problem; a quarter yard short is a ruined slab.
The subgrade warning: low spots eat concrete #
The formula assumes your base is exactly at the planned depth. It almost never is. Every low spot fills with concrete at full price.
The math is unforgiving. Take a 10 × 10 ft slab where a quarter of the base (25 ft²) sits 1 inch low. That dip holds 25 × (1 ÷ 12) = 2.08 ft³ of extra concrete, about 0.08 yd³.
That sounds small until you scale it. A base averaging half an inch low across a whole 20 × 20 slab quietly consumes over 0.6 yd³ you did not order. This is the single most common reason DIY pours run short despite "correct" calculations.
Prevent it before the forms are final:
- Screed the base to grade. Compact the gravel base. Then check depth from the top of the forms with a gauge block cut to your slab thickness. Work the block across the whole area on a grid.
- Fix lows with gravel, not concrete. Raising a low spot with compacted base material costs pennies. Filling it with concrete costs dollars per cubic foot and thickens the slab unevenly.
- Re-check after compaction. A base measured before compacting settles; measure again after.
Bags or truck? The decision at the end of the calculation #
Once you have your yardage, the delivery decision follows from the size:
- Under ½ yard (about 23 × 80 lb bags or fewer): bags, mixed on site. See how many bags are in a yard for counts in every size, or get exact numbers from the concrete bag calculator.
- ½ to 1 yard: your call. Choose bags with a rented drum mixer and a helper, or ready-mix if the short-load fee is modest.
- Over 1 yard: ready-mix, almost always. The worked example above (2.75 yards) would be about 118 bags and over 9,000 lb of dry mix to handle by hand.
Whichever route you choose, do the final check the same way: volume in feet, divide by 27, add waste, round up. Then, if you are pricing the job out, the figures in how much a concrete slab costs turn that yardage into a material budget. For shapes other than a simple rectangle (footings, post holes, round slabs), start from how much concrete do I need.