A standard mixer truck carries 8 to 10 cubic yards of concrete, and some trucks carry 11 yards. Your project probably needs far less than a full truck, and that is fine.
The real decision is not truck capacity. It is the size at which bags stop being cheaper and start costing you money, time, and slab quality.
At half a yard, bags win on cost. At one yard, the cost is a wash and the truck wins on labor. By two yards, the truck is ahead, and at five yards it wins decisively.
The table and timing rules below show why. The figures use $5.50 per 80 lb bag and $170 per yard for ready-mix. Check your own yardage first with the concrete yards calculator.
Truck facts you need before comparing #
A standard mixer truck carries 8 to 10 cubic yards. Some trucks carry 11 yards. Plants dispatch based on load, distance, and local road and bridge limits, so the plant will tell you the practical maximum for your address.
Most plants set minimums around 4 to 5 cubic yards for fee purposes. Orders below that range often carry a short-load fee of $40 to $100.
In the cost comparison below, the truck figures use $170 per yard plus a $75 short-load fee for orders under 4 yards. Your plant's fee may differ, but the structure is typical.
Place concrete within about 90 minutes of batching, and use less time in hot weather. That clock starts at the plant, not when the truck reaches your site. Dispatch timing, site readiness, and placement speed therefore matter.
A truck that arrives before crews finish the forms wastes the most valuable minutes of the pour.
A truck also needs access. Length, height, weight, and turning space all count.
If a truck cannot reach your forms, the comparison changes immediately. Bags, a pump, or a volumetric mixer then become the practical options, regardless of per-yard price.
The crossover analysis #
This table compares bag cost to truck cost at four sizes. Bag counts use 80 lb bags at $5.50 each. Truck cost uses $170 per yard plus a $75 short-load fee under 4 yards.
| Size | Bags (80 lb) | Bag cost | Truck cost | Winner |
|---|---|---|---|---|
| 0.5 yd3 | 23 x $5.50 | $127 | ~$160 + fees | Bags |
| 1 yd3 | 45 bags | $248 | $245 | Wash, truck on labor |
| 2 yd3 | 90 bags | $495 | $415 | Truck |
| 5 yd3 | 225 bags | $1,238 | $850 | Truck, decisively |
At 0.5 yards, bags cost $127 against about $160 plus fees for a truck, so bags win. The job is also small enough to mix and place without racing the set time across a large area.
At 1 yard, bags cost $248 and the truck costs $245. On price alone it is a wash. On labor it is not.
Forty-five bags need lifting, opening, mixing, and placing by hand. The truck delivers the same volume as one consistent mix in minutes.
At 2 yards, bags cost $495 against $415 by truck, and the truck pulls ahead on both price and effort. At 5 yards, bags cost $1,238 against $850 by truck. There is no serious argument for mixing 225 bags by hand to save money, because it does not save money.
Your local prices will shift the exact crossover, but not by much. If bags are on sale or ready-mix sits at the top of its range in your market, prices shift further.
Recompute with the concrete cost calculator and your plant quote. The labor argument in the next section still applies at the same sizes.
Time and cold joints: the real argument #
Cost understates the case for a truck. Time is the stronger argument.
A 3.5 cubic foot drum mixer handles about 2 bags per batch. Each batch cycle takes roughly 5 to 6 minutes, including loading. Forty-five bags for one yard therefore mean about 23 batches and more than 2 hours of continuous mixing.
That figure covers mixing time alone, before screeding and finishing. It also assumes no breaks.
Concrete does not wait for the mixer. The first batches placed start to set while later batches are still powder and water.
Where fresh concrete meets concrete that has already stiffened, you get a cold joint: a plane of weakness and a visible seam. On larger flatwork, hand mixing almost guarantees that early and late sections behave differently.
A truck eliminates that problem at normal residential sizes. The whole volume arrives as one mix, at one consistency. A small crew can place and finish it within its working time.
That uniformity is worth money even at the 1 yard size, where the invoice comparison is tied.
Hot weather shortens every window in this section. The roughly 90-minute placement limit shrinks, drum-mixed batches fall further behind, and finishing gets harder. If you pour in summer heat, weight the time argument even more heavily toward ready-mix.
When bags genuinely win #
Bags are the right choice in clear cases. The first is access.
Backyard work with only a narrow gate, steep ground, or no truck route can rule out delivery, no matter how good the per-yard price looks. Wheelbarrowing ready-mix over a long distance is sometimes possible. At that point, though, you pay truck prices for bag-level labor.
The second is tiny jobs. Setting a few posts, patching a small section, or pouring a single small pad under half a yard is tiny work. It does not justify a truck minimum or a short-load fee.
Bags let you buy exactly what the job needs.
The third is staged work. If you set posts over several weekends, bags let you work in stages. The same applies when you pour small sections that are genuinely independent, without wasting a delivered load.
Staging a single slab is different and risky, for the cold-joint reasons above. Staging separate footings is normal practice.
The fourth is remote sites. Where the nearest plant is far away, delivered concrete may be unavailable or priced for a long haul. The 90-minute clock may make it impractical anyway.
Bags travel in your own vehicle on your own schedule.
The middle options #
Between bags and a conventional truck sits the volumetric, or on-site, mixer. A volumetric truck carries dry ingredients separately and mixes concrete on site. You pay for what you use, and the truck typically avoids the short-load problem because it does not batch a fixed load at a plant.
Volumetric delivery suits jobs where your volume estimate is uncertain. It also suits jobs where you need small amounts at several spots on one site, or where a conventional minimum makes a standard truck wasteful. Fresh mixing on site also removes the long haul-time problem, because the truck mixes the concrete where you place it.
A pump is the other middle option, and it solves access rather than volume. If a ready-mix truck can reach your street but not your forms, a pump moves the concrete the last stretch. It adds cost, so use it when access or placement speed justifies it, not by default.
The decision in one line: bags under half a yard, and a hard look at both options at one yard. From two yards up, order a truck, unless access says otherwise.
Confirm your volume with how much concrete do I need. Then get one plant quote with the short-load fee stated, and compare it to the full bag count, not the price of a single bag.
Start from the homepage if you need a different calculator for your shape.