A footing calculation has two halves: the volume (length × width × depth in feet) and the sizing rules. The sizing rules tell you what width and depth to use in the first place. For a standard 16 x 8 inch footing, the volume is 8.89 cubic feet per 10 feet of run, or 0.33 cubic yards.

A typical 40-foot run of that footing needs 35.56 cubic feet, which is 1.32 cubic yards. Mixing on site, that run takes 60 bags at 80 pounds.

Widths, depths, and frost rules below reflect typical residential practice. Local code governs your project, and most jurisdictions inspect footings before the pour. Treat this guide as the math and the reasoning, and your building department as the final authority.

What a footing does #

A footing is a wide, flat pad of concrete under a wall or column. It spreads the load of the structure over enough soil to support it. A wall alone would concentrate the weight of the building on a narrow strip, and the soil under that strip would compress and settle unevenly.

Spreading is the whole job. Double the width of the footing and you halve the pressure on the soil under it. That is why footing sizing starts with the load and the soil, not with a standard dimension.

A footing that is too narrow fails slowly and expensively, by settlement. It fails long after the concrete itself has proven plenty strong.

Footings also anchor the structure at a stable depth: below the frost line, on undisturbed soil that does not shift with the seasons.

The volume math #

Volume is length × width × depth, with everything in feet. Convert inches to feet by dividing by 12: 16 inches wide is 1.333 feet, 8 inches deep is 0.667 feet.

Footing size (width × depth)Volume per 10 ftCubic yards per 10 ft
12 × 6 in5.00 ft³0.19 yd³
16 × 8 in8.89 ft³0.33 yd³
20 × 10 in13.89 ft³0.51 yd³
24 × 12 in20.00 ft³0.74 yd³

To use the table, divide your total run by 10 and multiply. A 40-foot run of 16 x 8 inch footing is 4 × 8.89 = 35.56 cubic feet. Divide by 27 for cubic yards: 1.32 yd³.

In 80 lb pre-mix bags, that run is 60 bags. That figure illustrates the point where ordering a small truck load beats mixing by hand.

Run your own dimensions in the footing calculator rather than scaling the table for unusual sizes, and add a waste allowance for trench irregularities. A hand-dug trench is never exactly its nominal width for its whole length, and the footing takes the shape of the hole you actually dug. Pair this with the general method in how much concrete do I need before you order.

Width rules #

Residential strip footings are typically 12 to 24 inches wide, with 16 to 20 inches common under one- and two-story walls. The wider end of the range serves heavier walls, two-story loads, and weaker soil.

The reasoning runs through soil bearing. Code tables commonly presume average soils bear about 1,500 pounds per square foot. The footing must be wide enough that the soil can carry the wall load.

Divide the total load of the wall above by the footing area, and keep the result within what the soil can carry. Weak or filled soil carries less, so the footing gets wider; strong undisturbed soil or rock carries more.

Thickness connects to width through the projection, the part of the footing that sticks out beyond the face of the wall. The footing's thickness should commonly equal or exceed that projection.

That thickness lets the concrete spread the load outward at a sound angle. The projecting edge then avoids becoming a thin, weak lip. A footing that grows wider must generally grow thicker too, which is why the standard sizes in the table pair width and depth together.

Do not widen a footing by digging a shallow, wide trench. Width without the matching thickness is not extra capacity.

Depth and frost #

Depth has two separate requirements, and your design must satisfy both.

First, the bottom of the footing must sit below the local frost line. When soil freezes, it heaves; a footing within the frost zone gets lifted unevenly, and the structure above cracks.

Frost depth runs from about 12 inches in mild climates to 48 inches or more in the northern United States. Your building department publishes the number for your area, and it is one of the first things to ask.

Second, the footing must bear on undisturbed soil. Topsoil, fill, and previously dug ground compress unpredictably.

If the trench at frost depth is still in loose or filled material, the footing goes deeper until it reaches firm, undisturbed ground. Where the trench is over-dug by accident, fill the excess with concrete, not with loose dirt shoveled back in. Loose backfill under a footing is a settlement waiting to happen.

Combined, these rules explain why two identical houses in different states have footings at very different depths. No national chart alone answers the depth question.

Stepped footings on slopes #

On a sloping lot, a footing does not follow the slope. It runs level, and steps down in level increments where the ground falls away.

Each step stays level. Crews keep vertical steps to footing-depth increments per code.

Horizontal and vertical sections overlap and carry reinforcement, so the whole footing acts as one piece rather than a staircase of separate blocks. Stepped footings need the same volume math, done step by step. Calculate each level run at its own length, add the concrete in the vertical steps, and total them in the footing calculator.

Reinforcement and inspection notes #

The typical residential strip footing carries 2 continuous #4 rebar running horizontally along its length. Continuous is the key word. The bars run the full length of the footing, lap where lengths join, and bend around corners rather than stopping at them.

That steel ties the footing together so a soft spot or minor settlement does not become a crack that travels.

Supports matter here too. Bars should sit on chairs or bolsters inside the footing. Keep 3 inches of cover where concrete meets earth, and keep bars out of the dirt at the bottom of the trench.

Finally, inspection. In most jurisdictions, an inspector checks the footing trench after crews dig and reinforce it, before anyone places concrete. Pouring before that inspection can mean tearing out finished work.